Information About Oil & Gas Development on Midland College Property

Information About Oil & Gas Development on Midland College Property

 

Midland College is committed to keeping the community updated with accurate information about oil and gas development on college property. 

Midland College's role in this project is limited to the college-owned property, the surface use agreement, and protecting the health, safety, and continuity of the college. This webpage provides information about Midland College's responsibilities only. Questions regarding drilling operations, engineering, permitting, environmental compliance, or emergency response are the responsibility of the project operator and applicable governmental agencies.

Midland College will update this page when new milestones are reached that may impact the students or community members and as they relate the to campus.

Project Summary

After thorough negotiations and legal review, the Midland College Board of Trustees approved an oil and gas lease and a Surface Use Agreement on March 2, 2026. These agreements limit surface operations to about 17.47 acres in the northeast part of the college property and set rules for safety, security, traffic, noise, lighting, dust, environmental care, and site restoration. 

The agreements were developed to: 

  • Protect the safety and comfort of Midland College students and employees. 
  • Preserve the functionality and appearance of the campus. 
  • Limit surface operations to a specifically designated area. 
  • Establish operating, security and environmental requirements. 
  • Protect the college’s long-term institutional interests. 
  • Allow responsible development of oil and gas resources.

Midland College will receive a $35 million lease bonus and approximately $25 million in royalties over the life of the project. Trustees also recognized the broader community impact, with local businesses and homeowners expected to receive an estimated $340 million and the City of Midland an estimated $198 million. 

Financial Information

What Will Midland College Receive? 

The approved Surface Use Agreement will provide Midland College with $35 million in compensation for surface use. 

Payment structure: 

  • $15 million (paid) within 30 days after execution and delivery of the Surface Use Agreement and oil and gas lease. 

  • $20 million (pending) upon the first of two specified events:
    • Thirty days after receipt of required permits for the initial well; or
    • 270 days after execution of the agreement.
  • Potentially $25 million in royalties paid over twenty-five years. 

How Will Midland College Spend the Money?

Midland College will continue to prioritize career and technical education (CTE).  At present, the college is turning students away in critical workforce programs such as welding technology, diesel technology, and energy technology.  The college is in the design phase of $77 million in new and expanded CTE facilities. 

Additionally, due to the loss of acreage, the college will explore a land purchase to accommodate future needs. 

Payment structure: 

  • $27 million dedicated to the construction of new CTE facilities. 
  • $8 million (estimated) purchase of land. 

Project Location & Campus Impact

Where Will the Project be Located?

The Surface Use Agreement identifies a designated drill site and access-road area in the northeast portion of Midland College property. 

  • A drill site of approximately 15.65 acres. 
  • A combined drill-site and access-road area of approximately 17.47 acres. 
  • Surface operations restricted to the designated premises. 

Map depicting the location of the oil and gas development project on the northeast end of the Midland College property.

How Does the Agreement Address Safety? 

The approved Surface Use Agreement includes measures to protect Midland College students, employees, visitors and property. 

Security and Access 

  • Security adjacent to the site during specified drilling, completion, workover and construction activities. 
  • Coordination with the Midland College Police Department. 
  • Gate-control measures during specified operations. 
  • Controlled use of the designated access area. 
  • A 20 mph speed limit on the surface premises. 
  • Compliance with applicable laws, ordinances and regulatory requirements. 

How will the campus and neighborhood impacts be addressed? 

Through the agreement, Midland College is committed to require the City and the operator to minimie disruptions to campus operations and the surrounding community. Plans are in place to manage potential impacts throughout the project, including noise, traffic, lighting, and dust. Select links below for more information. 

Before a drilling rig is moved onto the site, sound walls at least 24 feet high must be constructed around the drill site and along specified portions of the access road. 

The sound walls are required to remain during drilling, hydraulic fracturing and completion activities. 

The agreement also requires: 

  • Use of a quiet frac-fleet system. 
  • Sound-reduction technology. 
  • Other reasonably practicable measures to reduce noise. 

These requirements are meant to reduce noise, but they will not eliminate it completely. 

The agreement requires use of the designated access provisions and includes gate-control requirements during specified activities. 

The operator must use commercially reasonable efforts to avoid heavy-vehicle use of the access road between 8 a.m. and 5:30 p.m. on weekdays when scheduled classes or examinations are taking place. 

The agreement contains exceptions for certain activities, including: 

  • Rig-up and rig-down. 
  • Drilling. 
  • Completion. 
  • Unscheduled workovers. 
  • Emergencies. 

Traffic control measures, roadway access, and any required modifications to public streets are under the authority of the City and implemented by the operator in accordance with applicable permits and approvals. Midland College cannot guarantee that heavy vehicles will never operate during class hours.

Drill-site lighting must face away from the campus and be positioned and designed to minimize light reaching the campus to the extent reasonably practicable. 

The drill site and access road will use asphalt, approved caliche or comparable material intended to reduce dust. 

During construction, the site and access road must be kept wet as needed to avoid excessive dust. 

The following measures will help minimize visual impacts:

  • Temporary sound walls during specified operations. 
  • Permanent fencing at least 16 feet high. 
  • Materials and design intended to be compatible with Midland College aesthetics. 
  • Landscaping and irrigation plans subject to college review. 

Requirements related to environmental compliance and management of the site:

  • No drilling of water wells on the campus for project operations. 
  • No use of Midland College water wells or the college irrigation system for operations. 
  • No disposal by injection of saltwater, flowback water or other substances on the campus. 
  • No seismic operations on the campus. 
  • No burial of trash or debris on the property. 
  • Requirements related to environmental compliance, cleanup and remediation. 
  • Restrictions on flaring, subject to the terms of the agreement and City of Midland requirements. 
  • Use of electricity in drilling and completion activities as often and to the extent possible. 

The operator remains responsible for compliance with applicable municipal, state, and federal requirements. 

 

Questions from the Community

The questions below reflect topics raised by students, employees, neighbors, and community members. Midland College will continue to provide information as it pertains to our campus.

While nearby property owners are expected to receive about $400 million in royalties from the project, Midland College cannot determine or comment on individual mineral ownership. Property owners with questions about mineral interests should check their property records and consult a legal or title professional. 

According to the agreement, up to 30 to 50 wells can be drilled in the designated area, which covers about 17.47 acres. 

No surface operations are authorized throughout the campus. Surface oil and gas operations are limited to the defined surface premises. The agreement separately grants specified subsurface rights beneath the campus. 

The agreement prohibits drilling water wells on the campus and prohibits extracting water from Midland College water wells or its irrigation system. 

No. The agreement prohibits disposal by injection of saltwater, flowback water or other substances on the surface premises or elsewhere on campus. 

The operator must remove specified materials, plug and abandon wells according to applicable regulations, and restore disturbed property in accordance with the agreement. 

The agreement includes steps to reduce the impact on campus operations, such as traffic and noise. The operator will make reasonable efforts to avoid using heavy vehicles on the access road from 8 a.m. to 5:30 p.m. on weekdays when classes or exams are scheduled. 

 

Status Updates

  • Agreements have been fully executed by all parties: March 2, 2026
  • Site construction has begun DATE
  • Roadway entrance has been completed: June 23,2026
  • Sound wall construction has begun: July 14, 2026

 

Who To Contact

Project Questions

Operator/Developer

Permian Deep Rock Oil Company
Midland-Petro D.C. Partners

Traffic/City Ordinance Questions

City of Midland

Campus Questions

Midland College

 

Welcome

Midland College has many programs and options for our students. If you are investigating the opportunities we offer, our Welcome Center is the perfect place to receive general information.

Apply to MC Now

Thank you for choosing Midland College! Whether you are here to earn a few credits, take courses to transfer or start a new career, we welcome you.